What should a Transmission Operator do first during an unplanned transmission line outage?

Prepare for the NERC System Operator Exam. Leverage flashcards and multiple choice questions with explanations. Get ready for your test!

During an unplanned transmission line outage, the first action a Transmission Operator should take is to perform a Real-time Assessment. This step is critical because it allows the operator to evaluate the current state of the system, understand the extent of the outage, and assess any immediate operational impacts. The Real-time Assessment involves analyzing system data to determine how the outage affects overall system reliability, identifying any potential risks, and guiding subsequent actions.

This assessment helps the operator identify if there are immediate corrective actions needed to maintain system stability, such as redistributing loads or reconfiguring the network. By prioritizing this assessment, the operator can make informed decisions and communicate effectively with other stakeholders to ensure a coordinated response to the outage.

The other options, while important, are steps that typically follow after an initial assessment has been made. For instance, notifying public service commissions and conducting a damage assessment are necessary actions but are often part of a larger response plan that relies on the information gathered from the Real-time Assessment. Gathering data on previous operations can be helpful for analysis but does not address immediate issues arising from the unplanned outage. Therefore, performing a Real-time Assessment is the essential first step in managing the situation effectively.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy