What is the best action for Reliability Coordinator B regarding the low voltage transmission line in his area?

Prepare for the NERC System Operator Exam. Leverage flashcards and multiple choice questions with explanations. Get ready for your test!

Opening the low voltage transmission line is a proactive measure that can help prevent further complications such as overloads or potential equipment damage. When a low voltage transmission line is experiencing issues, it is often a result of operating conditions that put stress on the system, which can lead to reliability concerns. By opening the line, Reliability Coordinator B can stabilize the network, ensuring that the balance between supply and demand is maintained and reducing the risk of cascading failures or outages.

This action illustrates the responsibility of the Reliability Coordinator to prioritize system reliability and security. In contrast, removing a higher voltage line from service might create more significant disruptions in the grid and is usually not warranted unless specifically required to address safety or reliability concerns. Ignoring a request from another Reliability Coordinator can undermine collaborative efforts necessary for maintaining system reliability. Finally, proposing an alternative solution could be appropriate; however, in cases of immediate concern, the best course of action is often one that directly addresses the issue at hand, which in this situation is the low voltage transmission line.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy