What basis do Transmission Operators and Balancing Authorities use to determine necessary Operating Plans?

Prepare for the NERC System Operator Exam. Leverage flashcards and multiple choice questions with explanations. Get ready for your test!

Transmission Operators and Balancing Authorities utilize current or pre-determined operating situations that create a reliability concern as the basis for developing necessary Operating Plans. This is because these entities are primarily focused on ensuring the reliability and stability of the electric grid. When they identify specific operating conditions that may pose risks—such as anticipated peak loads, generator outages, or severe weather impacts—operating plans must be tailored to address these scenarios effectively. This proactive approach ensures that all necessary measures are in place to maintain system integrity and prevent operational failures.

This focus on existing or expected reliability issues guides decision-making and prioritization in operations, ensuring that responses to real-time or forecasted conditions provide a stable and reliable power supply to consumers. Consequently, such circumstances dictate the structure and content of Operating Plans to prepare for and manage potential disruptions within the transmission system.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy