When there is a sudden loss of generation in an external Balancing Area, the Automatic Generation Control (AGC) system plays a critical role in maintaining system reliability and balancing supply and demand. In this scenario, if the frequency bias setting is higher than the response required, it indicates that the system needs to increase generation to compensate for the loss.

The AGC continuously adjusts the generation levels within its Balancing Area based on the Area Control Error (ACE) and the frequency bias. If the frequency bias is higher than the response, it suggests that the measured frequency is lower than the desired level, prompting the AGC to respond by increasing generation to bring the frequency back to its set point.

Increasing generation in response to a generation loss helps stabilize the system and prevent adverse effects such as further frequency deviation or potential blackouts. This action leads to a positive outcome for system reliability.

In this context, maintaining system stability is crucial when faced with unexpected generation loss, making the AGC's response to increase generation the most appropriate and expected outcome.