How does a Dynamic Schedule differ from a Pseudo-tie?

Prepare for the NERC System Operator Exam. Leverage flashcards and multiple choice questions with explanations. Get ready for your test!

A Dynamic Schedule is designed to provide real-time updates to the flow of power between different areas or regions, reflecting the actual operating conditions and any changes in the grid. This real-time capability allows system operators to manage and optimize the flow of electricity more effectively, ensuring that any changes in generation or demand are accurately represented in the scheduling of power.

On the other hand, a Pseudo-tie typically involves a fixed schedule that does not account for real-time changes. It is used in cases where the actual physical flow of power is not directly controllable or measurable at every instant, so the power transfer is represented as a pseudo charge rather than an active, dynamic schedule.

The distinction in operation reflects how each approach affects system management—Dynamic Scheduling enhances responsiveness and operational accuracy, while Pseudo-ties simplify tracking of transfers but lack the same level of real-time integration. This uniqueness of the Dynamic Schedule and its real-time updating capability is what makes the third option the correct choice.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy