According to NERC Standard COM-002-4, how often must a Transmission Operator assess adherence to documented communication protocols?

Prepare for the NERC System Operator Exam. Leverage flashcards and multiple choice questions with explanations. Get ready for your test!

According to NERC Standard COM-002-4, a Transmission Operator is required to assess adherence to documented communication protocols at least once every 12 months. This annual assessment is crucial to ensuring that all communication processes are functioning effectively and that any updates to the protocols can be made based on current operational practices or changes in regulation.

Conducting this assessment on an annual basis helps maintain a high standard of communication reliability, which is essential for the safety and efficiency of electricity transmission operations. Ensuring protocols are followed and updated helps prevent miscommunication or operational failures that could impact grid reliability. The specified time frame recognizes the balance between needing sufficient oversight and not overburdening operators with too frequent assessments.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy