A Transmission Operator instructs the Generator Operator to change the MW output of their hydro plant to relieve an overloaded transmission line. This is an example of which of the following?

Prepare for the NERC System Operator Exam. Leverage flashcards and multiple choice questions with explanations. Get ready for your test!

The situation described is indeed an example of an operating instruction. An operating instruction is typically a directive issued by a Transmission Operator to a Generator Operator (or other relevant parties) that is aimed at managing the operational aspects of the grid. In this case, the Transmission Operator is addressing an overload scenario by instructing the Generator Operator to adjust the generation output of their hydro plant. This adjustment is being made to ensure the safety and reliability of the transmission system, indicating that it is a part of the normal operations and procedures carried out to maintain stability in the electricity supply.

Emergency procedures would involve responses to immediate and critical situations that threaten the operational integrity of the system and would require a more immediate and possibly drastic action, whereas compliance requirements refer to regulations and standards that must be adhered to by all operators, not specific operational adjustments. Reliability directives generally carry authority and may include enforceable actions but are typically issued under conditions that pose serious risk to system reliability, not just routine operational adjustments. In contrast, the scenario presented focuses on operational management rather than immediate emergency responses or regulatory compliance.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy